Preserving the old “Holbrook Mill” • one of the oldest structures in Aurora, Illinois


Progress to Date
(newest posts are at the top)


Holbrook Mill
July 21, 2009
IMG_7213 IMG_7210 IMG_7220 IMG_7228
IMG_7261 IMG_7270 IMG_7282 IMG_7330
IMG_7333 AFTER: Holbrook Mill - July 21, 2009  

Applause!!
The last stone piece of the giant-jigsaw puzzle was slid into place on the mill's front facade at about 4:00pm Tues 7/20/2009 (nearly one year and one month after the project began).

Holbrook Mill
July 20, 2009
IMG_7196 IMG_7198 IMG_7202 IMG_7206

The facade is nearly complete.

Holbrook Mill
July 17, 2009
IMG_6793_1 IMG_6788    

Work continues on the mill's facade.

Holbrook Mill
July 16, 2009
IMG_6781 IMG_6783 IMG_6784  

Holbrook Mill
July 15, 2009
IMG_6755 IMG_6757 IMG_6761 IMG_6763
IMG_6767 IMG_6777 IMG_6780  

Work begins on the mill's front (Benton St.) facade.  

Holbrook Mill
June 23, 2009
IMG_6501 IMG_6498 IMG_6497 IMG_6528
IMG_6558 IMG_6563 IMG_6523 IMG_6564
IMG_6529 IMG_6537 IMG_6538 IMG_6544
IMG_6503 IMG_6504 IMG_6520 IMG_6509
IMG_6511 IMG_6505 IMG_6507 IMG_6513
IMG_6553 IMG_6548    

Work continues on the mill's East (Middle Ave.) facade, while carpenters continue to add doors, and trim to the mill's interior.  

Holbrook Mill
June 22, 2009
IMG_6465 IMG_6467 IMG_6481 IMG_6485
IMG_6487 IMG_6475 IMG_6474 IMG_6473
IMG_6478 IMG_6490    

Workers begin installing the metal roof, while the masons creep higher on the mill's West wall.  

Holbrook Mill
June 18, 2009
IMG_6447 IMG_6450 IMG_6452 IMG_6453

The masons have the origional lime-stone installed about halfway up the mill's west wall, and are begining to hit their stride.  

Holbrook Mill
June 17, 2009
IMG_6429 IMG_6431 IMG_6434 IMG_6427
IMG_6422 IMG_6424 IMG_6421 IMG_6420
IMG_6439 IMG_6443    

Holbrook Mill
June 15, 2009
IMG_6412 IMG_6415 IMG_6419 IMG_6414

Work continues on the mill's west wall.

Holbrook Mill
June 12, 2009
IMG_6411 IMG_6404 IMG_6395 IMG_6408

Holbrook Mill
June 10, 2009
IMG_6378 A million-piece jigsaw puzzle<br>When the mill was disassembled, 140+ pallets of stone were salvaged.   Now comes the challenge of putting humpty-dumpty back together again. IMG_6377 IMG_6354
Steve Patzer - a Master at work.<br>June 9th, 2009, Steve (my master restoration mason) and his crew have begun the arduous task of putting the historic lime-stone back up on the exterior of the Mill. IMG_6348 IMG_6352 IMG_6339
IMG_6365 IMG_6372 IMG_6369 IMG_6363
IMG_6360 IMG_6361 IMG_6359  


Wahooo!!
The origional lime-stone begins to go up in the building's exterior. Steve Patzer and two other stone masons are starting on the building's west (parking lot) facade. Also today, the stairs are finished -- handrails and all -- and the hardwood floors.


Holbrook Mill
June 05, 2009
Second Floor - Interior of the old Holbrook Mill. <br>Reclaimed hardwood floors, stone interior walls and exposed trusses highlight the open-ceiling of the mill's second floor (residential) living space. IMG_6325 IMG_6326 IMG_6324
IMG_6328 IMG_6331 IMG_6332 IMG_6327
IMG_6333 IMG_6338    

Stone work is completed on the interior... Wood floors arebeing installed... doors and trim are on-site.


Holbrook Mill
May 28, 2009
IMG_6296 IMG_6300 IMG_6305 IMG_6303
IMG_6311 IMG_6318    

Soffits are completed, tall stone wall is completed and the masons are working on the kitchen wall.


Holbrook Mill
May 26, 2009
IMG_6263 IMG_6255 IMG_6280 IMG_6248
IMG_6285 IMG_6288 IMG_6279 IMG_6238
IMG_6241 IMG_6235    

Masons nearing completion of the tall stone wall.... The stairs are installed!


Holbrook Mill
May 20, 2009
IMG_6065 IMG_6064 IMG_6067 IMG_6071
IMG_6074 IMG_6078    

Steve Patzer, Ziggy (mason), and Manny (laborer) complete the second bedroom wall, and make great headway on the tall stone wall.


Holbrook Mill
May 19, 2009
IMG_6042 IMG_6053 IMG_6049 IMG_6050
IMG_6052 IMG_6059 IMG_6063 IMG_6058

Masons working on the wall in the second bedroom wall and begin the tall living room/entry wall... Garage doors are installed.


Holbrook Mill
April 29, 2009
IMG_5361 IMG_5425 IMG_5815 IMG_5817
IMG_5840 IMG_5843 IMG_5390 IMG_5900

Holbrook Mill
April 08, 2009
IMG_4961 IMG_5061 IMG_5077 IMG_5078
IMG_5079 IMG_5128 IMG_5132 IMG_5139
IMG_5140 IMG_5163    

Blow-in insulation is installed.... first it is blow-in, and it's then "shaved" even with the studs.


Holbrook Mill
January 27, 2009
IMG_1027 IMG_1029 IMG_1139  

Walls are framed, roof is enclosed.


Holbrook Mill
December 04, 2008
IMG_0901 IMG_0909    

Walls are framed, roof decking is completed.


Holbrook Mill
November 12, 2008
IMG_0516 IMG_0484 IMG_0502 IMG_0539
IMG_0494 IMG_0490    

Roof-decking continues....


Holbrook Mill
October 29, 2008
IMG_0453 IMG_0442 IMG_0450 IMG_0440
IMG_0456 IMG_0418 IMG_0415 IMG_0469
IMG_0465 IMG_0466    

Roof trusses are delivered and installed, work in the basement progresses.


Holbrook Mill
October 23, 2008
IMG_0348 IMG_0349 IMG_0333 IMG_0357
IMG_0361 IMG_0336 IMG_0341 IMG_0354

Second-floor walls coninue to go up, and the garage/office roof is framed.


Holbrook Mill
October 1, 2008
IMG_3676 IMG_3678 IMG_0309 IMG_0315

Second-floor walls go up, and the garage/office roof is framed.


Holbrook Mill
Sept. 22, 2008
IMG_3643 IMG_3646 IMG_3641 IMG_3653
IMG_3656 IMG_3661    

Walls are framed, roof is enlosed.


Holbrook Mill
Sept.16, 2008
IMG_3364 IMG_3365 IMG_3479 IMG_3480
IMG_3483 IMG_3485 IMG_3486 IMG_3490
IMG_3494 IMG_3496 IMG_3508 IMG_3512
IMG_3603 IMG_3606 IMG_3610 IMG_3613

First-floor walls go up...


Holbrook Mill
August 25, 2008
IMG_2936 IMG_2937 IMG_2941 IMG_2956
IMG_2926 IMG_2958 IMG_2966 IMG_2976
IMG_2992 IMG_2995 IMG_3009 IMG_3012
IMG_3041      

The concrete basement and foundation is poured....


Holbrook Mill
August 11, 2008
IMG_2782 IMG_2783 IMG_2784 IMG_2788

Basement and foundation is excavated....


Holbrook Mill
August 05, 2008
IMG_2707      

The building is “dismantled” and the site is leveled.


Holbrook Mill
July 31, 2008
IMG_2614 IMG_2615 IMG_2617  

The final walls are gentely nudged in upon themselves.


Holbrook Mill
July 29, 2008
IMG_2600 IMG_2606 IMG_2608 IMG_2611
IMG_2612      

Demolition is complete down to the first-floor walls.


Holbrook Mill
July 24, 2008
IMG_2531 IMG_2532 IMG_2535 IMG_2546
IMG_2540 IMG_2542 IMG_2565 IMG_2571
IMG_2553 IMG_2556 IMG_2559 IMG_2562
IMG_2573 IMG_2579 IMG_2581  

Second-floor walls and front facade is dismantled.


Holbrook Mill
July 22, 2008
IMG_2423 IMG_2458 IMG_2480 IMG_2483
IMG_2410 IMG_2426 IMG_2499 IMG_2495
IMG_2450 IMG_2444 IMG_2449 IMG_2448
IMG_2430 IMG_2453 IMG_2452  

Dismanteling continues.... Stone is stacked on pallets, shrink-wrapped, and stored off-site.


Holbrook Mill
July 21, 2008
IMG_2361 IMG_2356 IMG_2354 IMG_2348
IMG_2351 IMG_2350 IMG_2378 IMG_2381

Stone by stone, the work continues...


Holbrook Mill
July 17, 2008
IMG_2187 IMG_2184 IMG_2200 IMG_2192
IMG_2211 IMG_2236 IMG_2248 IMG_2234
IMG_2217 IMG_2224 IMG_2225 IMG_2226
IMG_2242 IMG_2191 IMG_2188  

Stone by stone, the the building is dismantled.... Stone is stacked on pallets, shrink-wrapped, and stored off-site.


Holbrook Mill
July 15, 2008
IMG_2067 IMG_2111 IMG_2118 IMG_2069
IMG_2138 IMG_2130 IMG_2154 IMG_2144
IMG_2073 IMG_2080 IMG_2163  

Work begins on dismanteling the building -- stone by stone....


Holbrook Mill
June 8, 2008
IMG_1971 IMG_1973 IMG_1976 IMG_1977
IMG_1978 IMG_1982 IMG_1989 IMG_1995

Crews from Braemoor Custom Homes being demolition of the building's second-floor interior storage-racks (used to store trim and molding when the building was part of White-and Todds Lumber Yard).


Holbrook Mill
June 8, 2008

Progress -- and lots of it!
As of June 5th, I've got a demolition (deconstruction) permit, I've selected a general contractor (Paul McCue's Braemoor Custom Homes), and -- most importantly -- I should be closing on the additional property needed from Old Second National Bank tomorrow morning at 10am! It has been a long road, but having a good team -- and I am confident that I do -- will make all the difference in the project's end result.

Next step... going green?
As my architect and I began finalizing the plans it became apparent that we had a wonderful opportunity to make this a “green” building project. Under Lane's direction I plan on making this a LEED (Leadership in Energy and Environmental Design) certified building -- the first in the City of Aurora, and one of only a handful in the western suburbs. LEED is a certification program created by the US Green Building Council that takes in a project's energy and environmental impact. A “green” building is not just about adding solar panels, or using recyclable materials, it is a building that encourages the use of less energy because of it's proximity to essential services (banks, schools, stores, and public transportation). It is a project that is more environmentally friendly during construction because it utilized old, existing, or reclaimed building materials (such as all the Holbrook Mill's original stone). By incorporating “Energy Star” appliances, compact florescent lighting, and innovative mechanical and ventilation systems, they are cheaper to operate and also healthier to live in.

We're still working through the application and design review process, but we'll proudly share some of our “eco- friendly” ideas and strategies as the project progresses. In the meantime, visit: United States Green Building Council's LEED for Homes page or the USGBC's Green Homes Guide for more information.


Summer 2007

Are you deconstructing it yet?
What's going on now!?

These are common questions, and the simple answer is, no not yet -- but hopefully soon. The architectural plans are being finalized, and I hope to begin the permitting process soon. Ultimately the project has been delayed by the ongoing negotiations to acquire the property needed for the garage addition, and a 5ft. set-back from the property line (as per fire code). The City of Aurora has been very supportive and we believe we have a solution which solves the issues, and yet still meets all fire codes.


Spring 2007

Any plans for restoring the Holbrook Mill need to be approved by two governing bodies -- the Aurora Historic Preservation Commission, and the Aurora Downtown Design Review Board. Both committees review the exterior elevations, the finishes, colors, and then comment/recommend changes to ensure the building blends in to the vision of Aurora's downtown. The Historic Preservation Commission is also watchful that a project meet national guidelines for preservation. This means that the windows should be of the "original" style (wood, double-hung, no vinyl cladding here), and that any new construction should be made of similar, but contrasting materials to delineate the addition, (which is why the garage addition is being constructed out of brick as opposed to limestone).

In February of 2007 both committees approved the plan for deconstruction of the mill, and the following month they approved the s plans for the building's reconstruction.


Summer 2006
David Lewis purchases the old Holbrook Mill.

 


HistoryPhotosPlansProgressPressContacts